SOTP Building Team
Weekly Construction Progress Report

Construction Progress Week # 6: September 15, 2017

Weekly Construction
  • Foundation walls finished and passed backfill inspection with Village of Huntley
  • Grouted and set the setting plates for the upcoming steel
  • Spot survey and the anchor bolt survey on new addition
  • Backfilled and put gravel base down for the slab on grade
  • Electrician starting to run conduits from existing electrical room towards new addition
  • SETTING STRUCTURAL STEEL NEXT WEEK!!!!!!! Things will be…LOOKING UP!!!!!!

Construction Progress Week # 5: September 8, 2017

  • Neil Concrete finished pouring foundation walls this week
  • Began preparing for backfill of foundation walls by putting wood strip and insulation on exterior of foundation walls
  • Little Lambs started first week of pre-school, and enjoyed the convenience and safety of being able to utilize the washroom facilities through their newly installed door
  • Owner’s meeting held Thursday, 9/7/17
  • Preparing for the setting of structural steel to begin 9/15, or 9/18/17

Construction Progress Week # 4: September 1, 2017

Weekly Construction
  • Poured north and some east foundation walls and the footings for THE ALTAR!
  • Working on forming the rest of the foundation walls towards a possible pour on 9/7/17
  • Coordination meeting held with Sound Planning and Shales McNutt regarding the sound system in the new Sanctuary

Construction Progress Week # 3: August 25, 2017

Weekly Construction
  • Fence installed around perimeter of construction area; Safety!
  • Concrete poured for exterior footings; 78 yards!
  • Interior walls begin to have concrete poured
  • Little Lambs classroom has exterior door installed to allow access to the playground
  • Little Lambs classroom has interior door installed to ladies bathroom for use by the Little Lambs children
  • Little Lambs classroom has one of the two hallway doors walled (west)
  • First Day of Little Lambs? Sept. 5th. All work to be completed by opening date

Construction Progress Week # 2: August 18, 2017

Weekly Construction Weekly Construction
  • Gates established on east and west entrances for sub-contractors
  • Preparation for concrete continues
  • Neil Concrete busy setting forms
  • Stark’s initial excavation complete and will be back next week to backfill
  • Additional Rock brought in to provide a solid foundation…

“On Christ the Solid Rock We Stand”

Construction Progress Week # 1: August 11, 2017

  • Sidewalk removed on east side of building
  • East building entrance/exit closed and to be used for emergency only
  • Bench by playground removed
  • Pin Oak tree that was on east side by bench replanted on north end
  • Stark begins digging trenches in preparation for concrete